Calculating Critical Path with Forward and Backward Pass - Key Concepts in Project Management

Calculating Critical Path with Forward and Backward Pass - Key Concepts in Project Management

101.028 Lượt nghe
Calculating Critical Path with Forward and Backward Pass - Key Concepts in Project Management
This video delves deeper into calculating the Critical Path on your Schedule Network Diagram by using the Forward and Backward pass. The steps are: 1. Note the task durations 2. Perform the forward pass to get early start and finish dates 3. Perform the backward pass to get late start and finish dates 4. Calculate float as Late Start minus Early Start 5. The critical path is the path with zero float #PMP #PMBOK #CAPM #ProjectManagement See all the Project Management Key Concepts (tools & techniques from the PMBOK Guide): https://www.youtube.com/playlist?list=PLEWFSKHjyrwycvU0Z0AeK5QfBIuyrYT0B